3 classroom, mess & toilet and bathrooms at P.T.S. Jalna
Status District Name Location
Completed JALNA JALNA
Unit Commander Address
Principal, Police Training School at Jalna. P.T.S., Jalna
Architect Vastu Shilp, Buldhana
Project Management Consultant Merog Project Planners & Management
Contractor Inderdeep Construction Co.
Scope of work i) Classroom - 1 Bldg. ii) Mess - 1 Bldg. iii) Toilet Block - 4 Nos
Built up Area ( in sqm) 1474.74
Work Order Date 28/01/2008
Project Exp.Cost (Rs in lakh) 201
Tendered Cost (Rs in lakh) 179.10
Date of Completion of Project 14/09/2008
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 6