Unconventional Operational Training centre & Special Action Group (Alpha Hawks) for SRPF XIII Nagpur | |
| Status | completed |
| District Name | Nagpur |
| Location | Surabardi, Nagpur |
| Postal Address | Principal UOTC, Nagpur |
| Government Administrative Approval Number/Date | / |
| Administrative Approval Amount | Rs 1,524.09 Lakhs |
| BoD Meeting / Item Note Number / Resolution No/Date | 139th BOD/ 15.09.2003 |
| Revised Administrative Approval Amount | Rs 4,044.00 Lakhs |
| Revised Board Resolution Number/Reference for Revision/Date | 180th BOD/ 24.03.2009 |
| Architect | Associated Architect |
| Project Management Consultant | Associated Architect |
| Contractor | Eagle Construction, Ulhasnagar |
| Scope of Work | 1) Administrative Bldg. – 1 No. |
| Built up Area | 19,311.46 sq mts |
| Project Cost | Rs 3,866.77 Lakhs |
| Estimated Cost | Rs 3,302.01 Lakhs |
| Tendered Cost | Rs 3,222.31 Lakhs |
| Work Order Date | 21/05/2009 |
| Time Limit for Completion | 20 months |
| Stipulated Date for Completion of Project | 20/01/2011 |
| Extended Date for Completion of Project | 20/06/2011 |
| First Extended Date for Completion of Project | 20/06/2011 |
| Liquidated Damages/Penalty | Rs. 1000/- per day from 14.12.10 Rs.5000 per day from 21.6.11 |
| Likely Date of Completion of Project | 25/09/2011 |
| Total Expenditure | Rs 3,901.58 Lakhs |
| Expiry date of defect liability period | 12 months/ |
| Status Remarks | |