Project Management Consultant |
PHC Engineer |
Scope of work |
a) Old (Stilt + 9th Floor) (Total 17 Nos. flats) = 3962.90 Sq.mtrs.
b) Revised (Stilt + 2 Podium + 13th Floors) = 8599.03 Sq.mtrs. |
Project Exp.Cost (Rs in lakh) |
1678.40 |
Tendered Cost (Rs in lakh) |
1636.63 |
Date of Completion of Project |
30/01/2013 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
12 |