Architect |
B.G.Shirke Const. Tech.Pvt.Ltd. |
Project Management Consultant |
PHC Engineer |
Contractor |
B.G.Shirke Const. Tech.Pvt.Ltd. |
Scope of work |
Original
Type II -320 Qtrs.
III 80 Qtrs.
Total : 400 Qtrs
Modified
Type II 108 Qtrs.
Type IV 28 Qtrs.
Total : 136 Qtrs |
Project Exp.Cost (Rs in lakh) |
3111.97 |
Tendered Cost (Rs in lakh) |
2700 |
Date of Completion of Project |
28/02/2015 |
Present Status |
Work completed and Handed Over |
Period of completion (in month) |
18 |